If you live or travel to the westside, nothing is more frustrating than road construction that never seems to end, especially along I-5 in Seattle.

A Concrete Makeover: Seattle's I-5 Ship Canal Bridge Is Looking New

The good news: the Washington State Department of Transportation has completed one massive project.

98.3 KEYW logo
Get our free mobile app

After 10 Months of Work, Seattle's Ship Canal Bridge Is Ready for Traffic

It took 10 months, but Seattle's Ship Canal Bridge is open to traffic again.

Amazing fact: it took about 23,000 wheelbarrows (roughly 200 truckloads) worth of new concrete.

A road work ahead sign laying on the ground
Photo by Danny Burke on Unsplash

READ MORE: Why Silverwood Letters Are Coming Down - People Shocked

Here are some other facts that might surprise you about the Seattle Ship Canal Bridge:

• Approximately 276 concrete repairs.
• Resurfaced more than 15,400 feet of bridge deck across all four northbound lanes.
• Restriped more than 74,000 feet of lanes and shoulders.

The new construction will extend the life of the bridge for many years to come and the WSDOT says it's a huge accomplishment in the Revive I-5 project. The lanes are open, and it should be smooth sailing for drivers.

All Northbound lanes are open, but get ready for 2027, as the Southbound lanes will be the next big project for the WSDOT.

Follow Us on Nextdoor

5 of the Friendliest Places To Live in Washington State

Here are my picks for the most-friendliest places to visit in Washington State - see if you have been to any of these places below

Gallery Credit: Rik Mikals

More From 98.3 KEYW